Building Update 3/27/24
Step Inside the Future of Learning at Triway!
We are excited to unveil a sneak peek inside the brand new PreK-12 building currently under construction.
This exciting animated flythrough takes you on a journey through the innovative learning spaces designed to empower and inspire our students.
The new building represents our commitment to providing an exceptional learning environment for every child in our district for many years to come.
Building Update 12/14/23
Building Update 10/10/23
Please click HERE if you’d like to see a flythrough of the current state of the building.
Building Update 8/1/23
Building Update 6/21/23
Building Update 6/9/23
Building Update 5/25/23
Building Update 5/16/23
Building Update 5/10/23
Groundbreaking Ceremony Video 4/20/23
Please click here to view the groundbreaking ceremony video.
Groundbreaking Ceremony
Please review the following information in preparation for Thursday’s One Triway groundbreaking ceremony.
The groundbreaking ceremony will be held in Lot A, closest to Shreve Road/State Route 226. This will cause the northern half of Lot A to be roped off for the event. The remaining open parking spots in Lot A will be reserved for guests with mobility concerns and handicap parking. These guests will enter Lot A using the temporary main entrance off of Shreve Road/State Route 226 (see included map).
We ask that all other traffic please enter from Valley Road, park in Lot B and Lot C, and walk to Lot A.
Please see the included ceremony agenda for additional information about the evening’s events.
Construction Update 4/12/23
Overall site
Elementary gym and kitchen area
Elementary wing foundations
High school and middle school gyms
Construction Update 3/29/23
Aerial view of the entire building site.
High school and middle school gymnasium walls
Building Update 3/16/23
Construction Update 3/10/23
Overall job site as of 3/9/23
Progress on the fire suppression system holding tank, located under the north side mechanical room
Start of the elementary gymnasium foundations
Progress on the high school and middle school gymnasium foundations, as well as beginning foundations for locker room spaces
Construction Update 3/8/23
Updated: Mar 10, 2023
In our last construction update, we communicated that due to winter conditions, we were expecting to have a dormant construction site until early spring. With a uniquely mild winter thus far, construction resumed mid-February. Much of the current activity is taking place underground, or is difficult to view from the vantage points on campus. In the coming weeks, vertical progress will be visible as gymnasium and auditorium walls begin to take shape.
Routine updates, mainly pictures, will highlight the exciting changes in our One Triway site. In addition to these updates, a live construction feed is available at Construction Feed | One Triway.
Overall job site as of 3/6/23
This 19 foot deep hole will house the 58,000 gallon fire suppression system holding tank, to be located under the north side mechanical room
Foundations for the high school and middle school gymnasiums on the southeast side of the building are in the early stages of being poured
Pathways for technology to the south side of the building
Deep trench on the west side of the job site for sanitary system work
Building Update 1/20/23
Our team of dedicated professionals from GPD Group and Hammond are working diligently to maintain our One Triway building project timeline. Public communications released in May showed the completion of the One Triway campus trending away from the fall of 2024 to the fall of 2025. Recent developments, and the productivity in the early site work, indicate the completion of the building trending toward winter of 2024. This could create a situation where our secondary schools (grades 6 - 12) move into the new building mid-year (December 2024).
A secondary mid-year move-in would allow for acceleration in the demolition and abatement of the current high school and middle school, which occupy the location of future parking lots. The development of these parking lots is critical in addressing the increased traffic from the transition of the elementary schools into the new building in the fall of 2025.
We are currently evaluating district systems, including school calendars, to ensure a smooth transition should a secondary mid-year move-in occur. While there are many construction related variables that could impact our timeline, we ask for your patience as we work through the implications of a possible mid-year move-in for grades 6-12.
We will continue to update the community on our progress as information becomes available. Thank you for your support of Triway Local Schools.
Building Update 1/3/23
Construction Update
In March of 2022, construction crews mobilized on site for the first phase of work to transform our district into the One Triway campus. The initial work focused on installing stormwater controls, select tree removal, and developing a new parking lot and temporary entry needed for the next phase of work. This past summer and fall, massive sitework occurred to prepare the building area for construction of the new PreK-12 school. This involved putting up additional storm water controls and starting underground utilities. Contractors graded the soil and transformed the site elevations to accommodate the future building footprint. Perimeter fencing and signage was installed as a part of Hammond Construction’s site safety plan, ensuring a safe and secure environment for students and staff throughout the building process.
The construction site will appear to be mostly dormant this winter; however, this is expected due to winter weather conditions. Site activity will resume in the spring after winter weather has passed. At that time, our community will celebrate a groundbreaking ceremony noting the start of the PreK-12 building construction. As soon as they are available, the details of this exciting event will be communicated.
New School Zone Approved
This past summer, an in-depth traffic study was conducted by traffic engineers from GPD Group. The Triway school administration, GPD, and Hammond worked with local officials, law enforcement, and Ohio Department of Transportation to analyze this study. Based on this analysis, a new school zone has since been approved, adding Valley Road to the current school zone plan. Traffic engineers are evaluating updated plans, in conjunction with state law, to identify the location of the new school zone. This includes the phasing in of new school zone signage, warning lights, and pavement markings along Valley Road.
Building Update 9/22/22
GPD, our architect firm, recently shared an exciting animated view of the exterior of the new PreK - 12 building. This is the first 3D view that shows all sides of the building and includes features such as the main entrances, play areas, parking lots, and potential location of the memorial garden. This animation reflects the building still in draft form as exterior finishes have not yet been finalized.
Click HERE for the OneTriway Exterior Animation
Building Update 9/9/22
Below you will find information on the new traffic pattern for Triway Middle School and Triway High School. Additionally, we have provided an animation to view this traffic pattern.
Click here to view the animation.
Building Update 8/17/22
Building Site Plan Update 5/17/22
Community Meeting 5/9/22
Triway Local Schools held a community meeting on 5/9/22 with information regarding the building project. Please click this link for a summary of the information shared during the meeting. Click here to view additional renderings.
Upcoming Site Work April 11-15, 2022
Project Informational Flyer 4/4/22
Building Update 4/4/22
Progress continues on development of the new Triway PK-12 campus. GPD and Hammond have been engaging with the school district administration and staff, board members, city officials, and various specialists to move the design forward. The district is committed to creating a facility that provides strong, innovative programs for students, safe and secure learning environments, and a gathering place for the Triway community.
Building Update 12/9/21
Updated: Apr 4, 2022
Plans for our new PK-12 building continue to evolve. After gathering valuable input on the first set of plans, significant changes include a more defined separation between elementary, middle and high school students; changing from three floors to two floors; and rotating the gyms and auditorium. The design is a work in progress, and we thank you for your continued support!
Building Update 12/9/21
As momentum begins to ramp up with our building project, we have added the final piece to our project team. Hammond Construction has been selected as our construction manager. This is a significant step as we move toward the next steps of the design phase, and the eventual ground breaking of our new facility. See below for more information about Hammond Construction and an introduction to the team working on our project.
Building Update 10/18/21
Updated: Apr 4, 2022
The new PK-12 building layout is beginning to take shape upon completion of intensive programming sessions with GPD Group. These sessions culminated in a Program of Requirements (POR) which is now being used to develop spatial adjacencies, refine departmental layouts, and analyze the building’s relationship with the site. Floor plans now reveal a general concept for placement of both academic and non-academic areas, while the site plan shows building orientation facing Shreve Road with a welcoming presence.
Building Update 7/22/21
Educational Visioning Summary
Meet the Architects
Building Update 4/22/21